REI Reopened – Pavement Project Complete

A $616,499 project to resurface the REI runway and west apron and replace striping was completed on Tuesday, November 19th. Construction started on November 12th and was originally estimated to continue until November 26th. The project was funded primarily with an FAA grant.

The resurfacing with approved coatings will enhance safety and extend the life of the pavement. The runway and west ramp look great!

THANK YOU to the contractor for getting the project done ahead of schedule, to the City of Redlands and the FAA for their commitment to improving REI’s runway and west ramp!

This entry was posted in Airport News, Notices. Bookmark the permalink.

Leave a Reply

Your email address will not be published. Required fields are marked *